SPI Web Site v1.1
IFC - International Finance CorporationIFC - International Finance Corporation -- » Reducing Poverty, Improving Lives...

Petronet

Summary of Proposed Investment

This Summary of Proposed Investment is prepared and distributed to the public in advance of the IFC Board of Directors’ consideration of the proposed transaction. Its purpose is to enhance the transparency of IFC’s activities, and this document should not be construed as presuming the outcome of the Board decision. Board dates are estimates only.

Project number 24902
Company namePetronet LNG Limited
CountryIndia
SectorUtilities
Environmental categoryB
DepartmentInfrastructure
StatusPending Disbursement
Date SPI disclosedApril 4, 2007
Projected board dateMay 10, 2007
Date revised SPI disclosedMay 4, 2007
Previous EventsSigned: June 23, 2007
Approved: May 31, 2007
View Environmental & Social Review Summary (ESRS), click here
  Overview     Sponsor/Cost/Location     Development Impact     Contacts     Attachments  

Project description
Petronet LNG Limited (PLL or the company) was established in 1998 to import liquefied natural gas (LNG), build and operate the related terminals and regasification facilities, and sell natural gas to distribution companies to meet India’s rapidly-growing energy needs. PLL currently has one 5 MMTPA operational LNG terminal and regasification facility (the Terminal) at Dahej, Gujarat, India, which was commissioned in April 2004. Regasified LNG (RLNG) from the Terminal is sold to Gas Authority of India Limited (GAIL), Indian Oil Corporation (IOC) and Bharat Petroleum Corporation Limited (BPCL) (the Offtakers), which is then sold by the Offtakers to end-consumers (mainly comprising power producers, fertilizer manufacturers and industrial units) in the region. The Terminal is connected to two main high pressure gas transmission networks currently in operation, the Hazira-Bijapur-Jagdishpur (HBJ) gas pipeline owned by GAIL and the Gujarat Gas Grid owned by Gujarat State Petronet Limited (GSPL) and connected via GAIL pipeline near PLL terminal. The work related to direct connection of GSPL line with PLL’s facility is underway. RLNG is transported through these networks under gas transportation agreements entered into between the Offtakers and network owners.

- PLL plans to:

- construct an additional regasification line, with its associated LNG storage tanks and if required a second jetty, to expand the capacity of the existing terminal at Dahej from the present 5 MMTPA to 10 MMTPA; and
- construct a greenfield 2.5 MMTPA LNG terminal (with provision for capacity expansion to 5 MMTPA) within Cochin Port area, at Kochi, in Kerala, both in India.

The project involves:

- at Dahej, installation of additional facilities within the existing terminal premises including 2 x 160,000 m3 gross capacity LNG storage tanks; 8 shell and tube vaporizers (STVs);
- 2 submerged combustion vaporizers (SCVs);
- 2 x 7.6 MW (ISO RATING) gas turbine generators (GTGs); and
- possibly a 5th 160,000 m3 gross capacity LNG storage tank and a second jetty (including a second LNG unloading system) if required, with doubling of the LNG tanker calls at the Dahej terminal from the present 80 tankers per year to 160 tankers per year; and
- at Kochi, construction of: LNG unloading jetty; dredging of basin;
- LNG unloading facilities including arms, pipelines and trestle for the pipeline;
- 2 x 155,000 m3 LNG storage tanks with provision for 3rd tank;
- LNG re-gasification system (2.5 mtpa capacity);
- plant utilities including 3 x 8 MW open cycle gas turbine, 6-7 MW grid electricity system, fresh water system, domestic and process waste water treatment system, compressed air, nitrogen and fire fighting system.

The principal associated facility, on account of the project, is the proposed RLNG transmission line from the LNG terminal to Coimbatore and Mangalore in Tamil Nadu and Karnataka, respectively, which will be laid, operated and maintained by GAIL.

The company has approached IFC for a corporate loan to fund its expansion program.