SPI Web Site v1.1
IFC - International Finance CorporationIFC - International Finance Corporation -- » Creating Opportunity...

EDF La Ventosa

Summary of Proposed Investment

This Summary of Proposed Investment is prepared and distributed to the public in advance of the IFC Board of Directors’ consideration of the proposed transaction. Its purpose is to enhance the transparency of IFC’s activities, and this document should not be construed as presuming the outcome of the Board decision. Board dates are estimates only.

Project number 28070
Company nameElectrica del Valle de Mexico S. de R.L. de C.V.
Country
Mexico (IDA)
SectorWind Power - Renewable Energy Generation
Environmental categoryB
DepartmentReg Ind, Infra & Nat Res, CAF/CLA
StatusActive
Date SPI disclosedDecember 22, 2009
Projected board dateFebruary 1, 2010
Previous EventsInvested: December 7, 2010
Signed: August 26, 2010
Approved: July 23, 2010
View Environmental & Social Review Summary (ESRS), click here
  Overview     Sponsor/Cost/Location     Development Impact     Contacts     Attachments  

Project description
Eléctrica del Valle de México S. de R.L. de C.V. (“EVM” or the “Company”) is currently developing and constructing a 67.5 MW greenfield wind power plant that consists of the installation of 27 Clipper “Liberty” wind turbine generators with a nominal capacity of 2.5 MW each, an associated substation and control facilities, and a 115 kV transmission line from the Project site to the Juchitán II substation of Comisión Federal de Electricidad (“the Project”).

The Project is located in the Ejidos of La Mata and La Ventosa in the Isthmus of Tehuantepec, 15 km north of the city of Juchitán in the State of Oaxaca, Mexico. The Project is configured as a line of 20 turbines in La Mata and a separate line of seven turbines in La Ventosa, both of which are approximately 2.5 km from the nearest community. The Isthmus of Tehuantepec has one of the most prolific wind resources globally, and the Project is expected to produce approximately 290 GWh annually on average over a 10 year period, which corresponds to approximately 49% capacity utilization. The Project is being developed under Mexico’s self-supply or “autoabastecimiento” framework and will supply its energy to four subsidiaries of Wal-Mart de Mexico S. A. B. de C.V. under 15-year self supply power purchase agreements.

Project construction is well advanced: all 27 turbines are erected, the substation and control facilities are complete and the transmission line is completed. According to current estimates, the Project is expected to be complete and commissioned by year-end 2009.