Case Studies




Contents
Finding a Mentor to Help Develop an EMS
Process Optimization in Textile Dyeing
Energy Saving in Soap Production


Finding a Mentor to Help Develop an EMS


Company A, a small Brazilian firm of ‘x’ number of employees, had two objectives in developing its EMS. First, it sought to create cost savings to re-invest in the company and second, it wanted to comply with environmental laws.

The first step the company took was to contact a supplier company that had previously implemented an EMS of its own with positive results. The supplier company agreed to serve as a mentor, sending staff to advise and help Company A implement an EMS and achieve its environmental objectives.

The staff from the supplier company advised Company A to prioritize its efforts by selecting areas and issues on which to concentrate, since all of the company’s concerns could not be addressed at once. The staff from the supplier company also suggested that Company A examine each operational phase, such as purchasing, process, products, transportation, rework, waste and packaging, to facilitate analysis. This approach provided ideas of where to start looking for potential environmental impacts.

Company A’s manager in charge of the operation worked with other employees involved in the process and identified six areas that would benefit from their resources and time. Company A also developed a “risk analysis summary” which drew on their best professional judgement to estimate the environmental hazardous risks for each of the six areas. Company A prioritized its projects and started taking measures to implement an EMS.

Six months later, the staff from the supplier company returned to Company A to help evaluate the results. They found that Company A had: Company A’s manager stated that the supplier company provided the advice and experience Company A needed to feel confident of putting a system in practice that would yield results and create a profit. In the manager’s words, “Once you get started, you’ll be surprised with your progress.” The president of Company A says that the new environmental system has become part of the company’s culture. Environmental issues are now considered in every decision involving capital expenditure and executives try to find the best environmental approach to take, given other constraints.

» Return to top

Process Optimization in Textile Dyeing


Company B, a textile hosiery processing industry in Ludhiana, India, bleaches and dyes cotton hosiery fabric on a job-order basis. Major process steps include scouring, bleaching, dyeing and finishing. The entire process is carried out using winches. After the first three steps, fabric is rinsed to remove extracted impurities and residual chemicals. After wet processing, the fabric is dried in a tubular steam hot air dryer. The company process about 4,000 kg of fabric per day, employs 150 people and has an annual turnover of about US$700,000.

Cleaner Production Assessment
Pressure from the Pollution Control Board to comply with environmental regulations was the catalyst for a Cleaner Production program. Other factors were a high fuel consumption (compared to other industries) and a high redye rate.

Cleaner Production Solutions
A Cleaner Production (CP) assessment identified 34 options, of which 22 have been implemented, including: Environment Benefits
Implementing 22 CP solutions resulted in the following environmental benefits: Financial Benefits
The company invested US$10,000 to implement 22 CP solutions, which resulted in annual savings of US$35,000 with a payback period of less than four months. Estimated total investment and annual savings for all 34 solutions would be US$260,000 and US$100,000 respectively.

» Return to top

Energy Saving in Soap Production


Company B located in Dar es Salam, Tanzania, is a private undertaking with 45 permanent staff members and 20 seasonal employees. It manufactures five tons of bar laundry soap per hour.

The soap is made from fat through a saponification process utilizing caustic soda. After a separating process the so-called "neat soap" is taken to a crusher, where it is mixed with pigment, perfume and other additives. The soap is then transferred to an intermediate tank from which it is fed into a vacuum flash cooling system. The cooled soap is then extruded in the form of bars, cut into size and packed in cartons.

Cleaner Production Assessment
The principal source of process energy is steam, which is generated from the combustion of industrial diesel oil in the boiler furnace burners. Steam is used throughout the whole process and for handling materials (unloading of fat from truck tankers, fat storage heating). The Cleaner Production (CP) assessment revealed leakages of steam from some of the valves and inefficient use of steam. The unloading of fat delivered to the factory resulted in spillage of 3,000 kg per annum. The spilled fat was absorbed by the soil.

Cleaner Production Solutions
In an effort to conserve steam energy and curb spillage of raw material, the project team recommended the implementation of the following CP options: Environmental Benefits
The boiler furnace consumption of industrial diesel oil was reduced by 54 percent to only 30 liters per ton of laundry soap produced, saving 415,800 liters per year. This measure also resulted in a considerable decrease in the emission COx, SO2 and NOx . The recovery of spilled fat also made a significant improvement to the direct environment of the factory.

Financial Benefits
The only option that needed some investment was the installation of steam valves, which cost US$830. All steam saving measures together resulted in annual savings of US$185,700. The payback time was only two days. Recovery of the spilled fat requires virtually no energy input, creating a savings of US$2,400 per year.

» Return to top

Increased Raw Material Efficiency in Pulp and Paper Production


Company C in Zhejinang Province, Republic of China, produces 51,000 tons of writing paper and cardboard annually and currently employs 5,000 people. About 18,000 tons of pulp are prepared annually from wheatstraw. The major operations of the plant are pulping, which includes straw preparation, batch mode cooking, washing, screening, hypochlorite bleaching, refining, stock preparing, black liquor extraction, alkali recovery and paper making.

Cleaner Production Assessment
Company C is one of the major contributors of pollution in Zhejinang Province. It is also a major consumer of energy and water. The pulping process, which contributed mostly to the high consumption and pollution load, was selected as the focus of the assessment.

Cleaner Production Solutions
In the assessment, 38 Cleaner Production (CP) options were generated. 22 no- or low cost options were selected for implementation along with four high cost options. Options requiring a substantial investment were the introduction of a computer control system for the operation of the cooking digestor, the installation of an additional causticizer and the repair of dust collectors and the caustic dregs washer. No- and low cost options included: The plant also decided to improve supervision of personnel and to introduce better operating procedures.

Environmental Benefits
The CP options implemented resulted in a significant decrease of the pollution load of more than 900 tons of COD on an annual basis. At the same time, the pulp yield was increased from 45 to 51 percent. The consumption of caustic soda is expected to decrease by 230 tons per year through the installation of a computer control system. Furthermore, significant water savings are being achieved.

Financial Benefits
The joint implementation of all selected no- and low cost options will result in annual savings of US$85,000. The implementation of the medium and high cost options, requiring an investment of US$55,000, will yield a total annual saving of US$161,000. Payback periods range from six months to one year.

» Return to top

Water Savings in Sugar Refining


Company F operates two sugar refineries in Harare and Bulawayo, Zimbabwe. The Harare plant was built in 1953 and its main equipment dates back to the same period. The factory runs seven days a week, twenty-four hours a day and has a yearly production of 140,000 tons of refined sugar. The factory employs approximately 500 people.

The refineries receive raw sugar from sugar cane mills and process it into refined white sugar. White sugar is produced for the local market and for regional export. This case study follows the assessment in the Harare factory.

Cleaner Production Assessment
The focus of the Cleaner Production (CP) assessment was on water conservation, as a long drought had resulted in severe water shortage and rationing in Zimbabwe. The sugar refinery was faced with high surcharges when the water consumption level exceeded the allocated amount. The most significant sources of water loss included:

Approximately 42 m3 of fresh water used daily to wash the bagasse originating from the clarifier into the sewage system.
Cleaner Production Solutions
The following CP solutions have been implemented:
Environmental Benefits
The implementation of the three options is projected to reduce the water consumption by approximately 86,000 m3 annually. Solid wastes to the municipal sewer is projected to be reduced by 120 tons per year.

Financial Benefits
The factory invested US$ 28,000 for the reduction of water consumption. With an expected saving of US$ 24,000 per year on water charges, payback period will be 14 months, not considering any possible surcharges for which the company may have been responsible.

» Return to top


«
Chapter 8 | Chapter 10 »